Slow Progress Draws Concern as DC Reviews NH-102B Highway Packages in Churachandpur

The District Administration, under the leadership of Deputy Commissioner Shri Dharun Kumar S, conducted an extensive field inspection along the NH-102B corridor to review progress of ongoing highway works being executed by the National Highways & Infrastructure Development Corporation Limited (NHIDCL).

Accompanied by ADC Mualnuam Shri Thangboi Gangte, the inspection focused on project sites across multiple construction packages that are crucial for improving road connectivity within the district and strengthening Manipur’s internal transport network.


Slow Progress in Packages 4A & 4B Sparks Concern

During the ground verification, officials observed delays in Packages 4A and 4B. Expressing disappointment over the sluggish pace of work, the Deputy Commissioner directed NHIDCL engineers and contractors to step up construction immediately, stressing that the State’s limited working season — heavily restricted by rainfall and terrain conditions — demands maximum utilisation of every operational day.

“Work must move on a war-footing. Every available dry day counts,” the DC reportedly told project officials on site.


Clear Directives for Timely Completion

The district administration also issued instructions to ensure that progress remains uninterrupted on Packages 2A, 2B, 3A, and 3B, with deadlines to be strictly adhered to. Officials emphasised that highway delays directly affect economic mobility, access to healthcare, education transport, and emergency response — especially in remote hill areas where alternatives are limited.


District Review Meeting Held at Mualnuam

Following the inspection, the Deputy Commissioner chaired a District Review Meeting at the Mualnuam Sub-Divisional Headquarters, bringing together:

  • Additional Deputy Commissioners (ADCs)

  • District Level Officers (DLOs)

  • NHIDCL representatives

  • Line department heads

Each department presented progress updates and outlined key developmental milestones achieved across the district.


Inter-Departmental Coordination Stressed

The meeting underlined the need for stronger coordination between line departments and project implementing agencies to ensure that infrastructure development proceeds alongside health, education, drinking water, and rural development initiatives.

Officials discussed implementation bottlenecks such as:

  • Weather disruptions

  • Machinery deployment issues

  • Labour availability

  • Logistical delays in remote zones

To address these gaps, district leadership called for synchronised planning schedules, improved field supervision, and faster reporting mechanisms so that corrective measures can be taken without delay.


Why NH-102B Matters

NH-102B remains one of the most critical connectivity links for Churachandpur district, connecting interior settlements to district headquarters, state capitals, and trade corridors. Improved sections of the highway are expected to:

  • Reduce travel time significantly

  • Improve movement of essential supplies

  • Support commercial transport

  • Enhance access to government services

With the State facing developmental challenges compounded by difficult terrain and periodic disruptions, timely completion of the highway has become a development priority.


District Administration’s Commitment

Concluding the day’s review, DC Dharun Kumar reinforced the district administration’s commitment to rigorous field monitoring and transparency, stating that regular inspections would continue until all packages achieve satisfactory progress benchmarks.


✅ NH-102B Status Snapshot

Package Status Administrative Direction
2A & 2B Ongoing Maintain pace
3A & 3B Ongoing Complete within schedule
4A & 4B Delayed Accelerate on war-footing